Austria: Small hydropower plant “Königsberg”



Project description

  • Planning and tendering of a small hydropower plant in Hollenstein an der Ybbs

RIVEROs tasks

  • Design of the headrace pipeline, valve chambers, etc.

  • Preparation of the corresponding tender documents
  • Preparation of the documents for the approval of forest clearing

Project data

  • Location:

    Hollenstein an der Ybbs, Austria
  • Lead Company: David Steinbacher ZT, Hollenstein an der Ybbs
  • Project Start: 10/2022
  • Project End: 04/2023